City of Lawrence in Process of CIP Approval
July 8, 2023
The City of Lawrence is in the process of the 2024-2028 Capital Improvement Plan (CIP).
The projects included in the 2024 CIP have been identified and scored using a “prioritization matrix,” then peer reviewed by subject matter experts and recommended to the city manager by the city’s CIP Committee.
Projects involving the Lawrence Loop include:
- Lawrence Loop – Iowa Crossing
- planned for 2024
- Lawrence Loop – Michigan to Sandra Shaw Park- funded for 2024
- planned for for 2024
- Lawrence Loop Trail – Kaw River -7th street to Constant Park
- planned for 2024 – 2026
- Lawrence Loop Trail from Queens Rd to Kasold
- planned for 2025 – 2027
- Lawrence Loop – Clinton Parkway Crossing
- planned for 2027 – 2028
The CIP is just one piece of the city’s annual budget process. The next step will take place July 11, when City Manager Craig Owens will present the commission with his recommended 2024 budget.